AS 3745-2010 · Western Australia
Evacuation diagram requirements in WA, explained
Everything AS 3745-2010 says about evacuation diagrams, translated into plain English for school leaders, business owners and facilities managers in Western Australia. Minimum elements, size, mounting height, orientation, validity dates and when a diagram has to be updated.
- Trusted by 300+ WA schools
- 4.9★ Google rating, 85 reviews
- Every diagram drawn to AS 3745-2010

The short version
What the standard actually requires
AS 3745-2010 Planning for emergencies in facilities is the Australian Standard behind every emergency plan in a WA workplace or school. Clause 3.5 is the part that deals with evacuation diagrams, and it is short: diagrams must be displayed where people can see them, mounted at a sensible height, oriented to the wall they hang on, and carry a fixed list of minimum elements.
In Western Australia the standard sits underneath the Work Health and Safety Act 2020 and the WHS (General) Regulations 2022, which require every business, school and building operator to prepare and maintain an emergency plan. Following AS 3745-2010 is how you show that has been done.
The standard does not set a replacement interval for diagrams. What it does require is that they are kept accurate: when the building, exits, fire equipment or assembly area change, the diagram changes too.
- Clause 3.5.2: displayed where occupants and visitors can view them
- Clause 3.5.3: mounted 1200 mm to 1600 mm above the floor
- Clause 3.5.4: oriented to the direction of egress and the YOU ARE HERE point
- Clause 3.5.5: fourteen minimum elements, including a validity date and legend
- Clause 3.5.7: minimum A4, or A3 when extra information is included
- Section 8: inspected, tested and maintained, with records kept
What Craig provides
Diagrams are one stage of the six-stage emergency management framework CMG uses across WA:
By the numbers
The figures auditors check first
1200 to 1600 mm
Mounting height
Clause 3.5.3. The diagram sits within this zone above the finished floor so adults and older students can read it at a glance.
A4 minimum
Diagram size
Clause 3.5.7. A4 for the minimum elements only; A3 as soon as anything extra is added, with the floor plan itself at least A4.
200 × 150 mm
Floor plan size
Clause 3.5.5(a). The pictorial plan of the floor or area must be at least this size on every diagram.
14 elements
Minimum content
Clause 3.5.5. From the title and YOU ARE HERE point through to the validity date, assembly area and legend.
12 months
Evacuation exercises
Clause 7.3. Every area of the facility takes part in at least one emergency response exercise in each 12-month period.
0 fixed years
Replacement interval
The validity period should not exceed five years (clause 2.2), and a diagram must be updated sooner whenever the building, exits, equipment or assembly area change.
Clause 3.5.5
The fourteen minimum elements
Every evacuation diagram, in every building, must show all of these. Miss one and the diagram is non-compliant, however good it looks.
- A pictorial plan of the floor or area (200 mm × 150 mm minimum)
- The title EVACUATION DIAGRAM
- The YOU ARE HERE location
- Designated exits, in green
- Warden intercommunication points, in red
- Manual call points (red) and emergency call points (white or black border)
- Main controls or panels for the occupant warning system
- Hose reels, in red
- Hydrants, in red
- Extinguishers, in red with the AS/NZS 1841.1 colour band
- Fire blankets, in red
- Fire indicator panel, if provided
- Refuges, if present
- Validity date, assembly area and a legend matching the symbols
Real CMG diagrams
What a compliant diagram looks like
Diagrams CMG has drawn and installed in WA schools and campuses, each carrying every minimum element, the full site address and oriented to the wall it hangs on.








Interactive self-check
Is your evacuation diagram still compliant?
Six quick checks based on AS 3745-2010 and what Craig sees most often on WA sites.
Does every diagram have a "You Are Here" point that matches where it is mounted?AS 3745-2010 requires the diagram to be oriented to the viewer's position.
Are all current exits and paths of travel shown, with nothing that no longer exists?Blocked, locked or removed doors are the most common failure.
Is the assembly area shown correctly, including any temporary changes?Construction, transportables and new fencing often move it.
Is every extinguisher, hose reel, blanket and alarm point shown where it actually is?Equipment gets relocated during fit-outs and services.
Has the building changed since the diagram was issued?Extensions, new rooms, demountables or a changed use of space.
Is the diagram legible, with a legend, and mounted at the right height?Faded prints and missing legends are non-compliant.
Answer the six checks above
Takes under a minute. We will tell you plainly whether your diagrams are likely to stand up.
AS 3745-2010 FAQs
Twenty-nine questions, answered plainly
Grounded in the clauses of AS 3745-2010 and WA workplace legislation. If your question is not here, Craig will answer it on the phone.
What is AS 3745-2010?
AS 3745-2010 Planning for emergencies in facilities is the Australian Standard that sets out the minimum requirements for an emergency plan in a building or workplace. It covers the emergency planning committee, the emergency plan and response procedures, the emergency control organisation (wardens), evacuation diagrams, training and evacuation exercises. It is the fourth edition, superseding AS 3745-2002.
Is AS 3745-2010 law in Western Australia?
AS 3745-2010 is a standard, not legislation, but it is the benchmark regulators and insurers use. In WA the Work Health and Safety Act 2020 and the WHS (General) Regulations 2022 require a person conducting a business or undertaking to prepare, maintain and implement an emergency plan, and following AS 3745-2010 is the accepted way to show that duty has been met. Schools, councils and most commercial leases also reference the standard directly.
Which buildings need evacuation diagrams?
Clause 1.2 applies the standard to buildings, structures and workplaces occupied by people. The only exclusion is a Class 1a dwelling (a house, townhouse or villa) unless it is also used as a workplace. In practice that means schools, childcare centres, offices, shops, warehouses, factories, laboratories, hospitality venues, aged care, medical practices, community buildings and strata common areas all need them.
Do schools in WA need evacuation diagrams?
Yes. Schools are facilities occupied by people and are not exempt from AS 3745-2010 or the WHS Regulations. Public, Catholic, independent and early learning sites all need compliant diagrams in every building, oriented to where each one is mounted. CMG has worked with more than 300 WA schools on exactly this.
What must an evacuation diagram include?
Clause 3.5.5 lists the minimum elements: a pictorial plan of the floor or area at least 200 mm by 150 mm; the title EVACUATION DIAGRAM; the YOU ARE HERE point; designated exits in green; communications equipment such as warden intercommunication points and manual call points where installed; hose reels, hydrants, extinguishers and fire blankets in red; the fire indicator panel if provided; refuges if present; a validity date; the assembly area in words or on a plan; and a legend that matches the symbols used.
What are the optional elements on an evacuation diagram?
Clause 3.5.6 lets the emergency planning committee add the direction doors open on exits, a north point, first aid kits (white cross on green), hazardous chemical stores, spill kits, emergency phone numbers and procedures, warden details and paths of travel in green. CMG typically includes paths of travel and first aid points because wardens and visitors find them useful.
What size does an evacuation diagram have to be?
Clause 3.5.7 sets a minimum of A4 (210 mm by 297 mm). If any additional information beyond the minimum elements is added, the diagram must be at least A3 (297 mm by 420 mm) and the floor plan itself must be at least A4. Most CMG school and commercial diagrams are produced at A3 for legibility.
How high should an evacuation diagram be mounted?
Clause 3.5.3 says the diagram should be positioned within a zone not less than 1200 mm and not more than 1600 mm above the finished floor. That puts it at eye height for most adults and still readable for older children.
Where should evacuation diagrams be located and how many do we need?
Clause 3.5.2 requires diagrams to be displayed where occupants and visitors can view them. The number and location is decided by the emergency planning committee for the facility. As a rule of thumb CMG recommends one at every main entry, in corridors near exits, in staff rooms and in any room where visitors wait or gather. A multi-block school will usually need one per block per level at minimum.
What does orientation mean for an evacuation diagram?
Clause 3.5.4 requires each diagram to be oriented to the direction of egress and its location relative to the YOU ARE HERE point. In plain terms, if you are standing in front of the diagram the exit on your left should be drawn on the left. Any assembly area inset must share the same orientation. A diagram copied from one wall to another without re-orienting is one of the most common non-compliances CMG finds.
What is the validity date on an evacuation diagram?
Clause 3.5.5(l) requires a validity date on every diagram. It tells wardens and auditors when the diagram was issued or last confirmed as correct. It is not an expiry date set by the standard; the Emergency Planning Committee decides how long a diagram remains valid, up to five years,, and it must be re-issued sooner if the building changes.
Do evacuation diagrams have to be replaced every five years?
AS 3745-2010 asks the Emergency Planning Committee to nominate a validity period for the emergency plan and diagrams, and notes that it should not exceed five years (clause 2.2). Craig recommends a full review at least every five years. Section 8 also requires the emergency plan and its elements, including diagrams, to be inspected, tested and maintained, and any deficiency to be rectified with minimum delay. What triggers an update is change: new rooms, demountables, relocated exits or equipment, a changed assembly area, or a diagram that has faded or gone missing. CMG reviews what you have and updates only what needs it.
When do our evacuation diagrams need updating?
Whenever the diagram no longer matches the building. Typical triggers are a refurbishment or extension, new transportables, a changed use of space, doors locked or removed, fire equipment moved during a service, a new assembly area because of construction or fencing, or a validity date that has passed. If you are unsure, a quick walk-through against each diagram will tell you.
Who is responsible for evacuation diagrams in a workplace?
Under the WHS laws the person conducting the business or undertaking (the employer, school or building operator) holds the duty. AS 3745-2010 places day-to-day responsibility with the emergency planning committee (EPC), which decides the number and location of diagrams and approves their content. CMG works with the EPC, principal, business manager or facilities manager to get them right.
What is an emergency planning committee (EPC)?
Section 2 of AS 3745-2010 requires each facility to have an EPC responsible for developing, implementing and maintaining the emergency plan, including evacuation diagrams, appointing the emergency control organisation and arranging training and exercises. In a school it is often the principal, business manager and a senior teacher; in a workplace it is usually management plus a safety representative.
What is an emergency control organisation (ECO)?
The ECO is the warden structure: chief warden, deputy, area wardens and wardens, plus first aid officers where appointed. Section 5 of the standard covers their roles, authority, selection and identification (the familiar coloured helmets or vests). The ECO acts on the procedures in the emergency plan until the fire brigade or other emergency service arrives.
What is the difference between an emergency plan and an evacuation diagram?
The emergency plan is the whole document: emergency identification, response procedures, the EPC and ECO structure, training and review arrangements. The evacuation diagram is one element of that plan, the part that is displayed on the wall for occupants and visitors (Figure 3.2 in the standard). CMG can prepare either or both.
How often should evacuation drills be held?
Clause 7.3 requires a program of emergency response exercises for each facility, with all areas of the facility taking part in at least one exercise in every 12-month period. New procedures should be tested within the first 12 months of implementation (Clause 7.2). Each exercise should have observers, a debrief and a report to the EPC.
Do fire wardens need training?
Yes. Section 6 requires ECO members to be trained before taking on the role and to maintain their skills through refresher training and exercises. Clause 6.5 covers skills retention. CMG delivers on-site fire warden, extinguisher and evacuation training across WA so the whole team is trained on the same day.
Do we need to keep records?
Clause 8.1 requires records of all inspection, testing and maintenance activities, and Clause 7.1 requires a report to the EPC after every exercise. Keep copies of each issued diagram, the date it was installed, exercise reports and training attendance. Auditors and insurers will ask for them.
What colours must be used on an evacuation diagram?
The standard is specific: exits and paths of travel are green, fire hose reels, hydrants, extinguishers, fire blankets, manual call points and warden intercommunication points are red, and emergency call points are white or have a black border. Extinguishers also carry the colour band from AS/NZS 1841.1. First aid points, if shown, are a white cross on green.
Does the assembly area have to be shown?
Yes. Clause 3.5.5(m) requires the assembly area to be stated in words or shown pictorially. Where it is drawn as an inset, Clause 3.5.4 requires the inset to have the same orientation as the main diagram. Temporary changes to the assembly area, for example during building works, should be reflected in an updated diagram.
Can we produce our own evacuation diagrams?
Nothing in the standard stops you, but the diagram must meet every minimum element, be correctly oriented for each mounting point and be drawn from an accurate floor plan. Most non-compliant diagrams CMG sees were drawn in-house from an old architectural plan, copied to several walls without re-orientation, or missing the legend, validity date or assembly area. Having a specialist draw them is usually cheaper than fixing them after an audit.
Are laminated or framed diagrams acceptable?
The standard does not specify the finish. What matters is that the diagram is legible, mounted in the 1200 mm to 1600 mm zone, and stays in place. CMG supplies framed, laminated or acrylic-mounted diagrams depending on the site, plus a PDF copy for your records.
Do strata and residential buildings need evacuation diagrams?
Apartment buildings (Class 2) and the common areas of strata schemes are facilities occupied by people and are covered by the standard. Only Class 1a dwellings (houses, townhouses and villas) are excluded, and even those are covered if used as a workplace.
What are the penalties for non-compliance in WA?
Non-compliance with AS 3745-2010 itself is not an offence, but failing to prepare and maintain an emergency plan is a breach of the WHS (General) Regulations 2022, which carry significant penalties for businesses and officers. More commonly, missing or inaccurate diagrams are picked up during Department of Education audits, insurer inspections, lease handovers and fire service inspections, with a deadline to fix them.
How long does it take to get compliant evacuation diagrams?
For most Perth sites CMG surveys, draws, proofs and installs within a few weeks. Where CMG already holds your drawings from previous work, updates are faster. Regional WA sites are grouped into trips so the travel is efficient.
Does CMG review existing diagrams before replacing them?
Yes. Craig checks each diagram against the building, the mounting position and the AS 3745-2010 minimum elements, and quotes only for what actually needs changing. Diagrams that are still accurate stay on the wall.
What else is covered by AS 3745-2010 besides diagrams?
The standard covers the whole emergency management picture: forming the EPC, identifying the emergencies relevant to your site, writing the emergency plan and response procedures (including bomb threat and civil disorder in the appendices), appointing and training the ECO, personal emergency evacuation plans for people with a disability, communication systems, exercises and ongoing review. CMG follows the same six stages on every site.
Talk to Craig
Not sure your diagrams meet the standard? Craig will tell you plainly.
Send a photo of a diagram or tell Craig what has changed on site. He will tell you whether it still complies, and quote only for what actually needs updating.